If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.
Correct Answer:
Verified
Q17: A hierarchical listing of what must be
Q18: The path in a network with the
Q19: The probability of occurrence of risk events
Q20: Path probabilities are calculated by dividing path
Q21: The earliest finish time for an activity
Q23: One upside to terminating a project that
Q24: Project management software eliminates constraint violations when
Q25: The task of identifying risks should involve
Q26: The standard deviation of the critical path
Q27: If two consecutive activities have shared slack,