The direct labour hours required to produce the first two units of a new product are 2,000 and 1,800, respectively. Using a 90% learning rate the company would estimate the direct labour hours for the 5th unit to be
A) 1692.4 hours.
B) 1620.0 hours.
C) 1566.0 hours.
D) 1523.2 hours.
Correct Answer: