A dummy activity is an activity inserted into the network diagram to show a precedence relationship, but does not represent any passage of time.
Blooms: Comprehension
Correct Answer:
Verified
Q3: A project team is typically cross-functional consisting
Q7: The principles of total quality management (TQM)cannot
Q8: Managing quality is not an important part
Q10: The critical path is the shortest path
Q12: The three major components of project management
Q13: Earned value analysis reports a project's performance
Q17: The upper level of a work breakdown
Q17: Use Smartsheet for CPM/PERT analysis.
Q20: In general,projects are subject to less uncertainty
Q40: Activities that are not on a project's