All of the following options are inputs into the MRP process except the
A) master production schedule.
B) product structure file.
C) item master file.
D) planned order report.
Correct Answer:
Verified
Q11: ERP systems are only concerned with production
Q24: The application modules that comprise the ERP
Q36: Enterprise resource planning integrates business processes at
Q39: Capacity requirements planning (CRP)projects the load from
Q40: ERP application modules can be used alone
Q40: Load levelling is used to resolve the
Q41: Given the following MRP matrix for Item
Q42: Given the following MRP matrix for Item
Q43: Given the following MRP matrix for Item
Q44: Given the following MRP matrix for Item