The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is the
A) shortest processing time (SPT) .
B) Johnson's Rule.
C) assignment method.
D) minimal slack rule.
Correct Answer:
Verified