Consider a project network that begins with activity X and is followed by activity Y. The earliest start time for activity X is 5 days and it will take 3 days to be completed. The earliest start time for activity Y is 12 days. Given this information, activity X has _____ of free slack.
A) 20 days
B) 4 days
C) 12 days
D) 9 days
E) 15 days
Correct Answer:
Verified
Q74: The scum master develops estimates for the
Q75: Agile velocity is not impacted by the
Q76: Nessage Mique, a niche fashion boutique, displays
Q77: A Term not used in the discussion
Q78: Verita Nist, an automobile company, sought to
Q80: Minkset Blu, a textile company, wants to
Q81: Technical dependencies on a project plan are
Q82: Rico Gen, a sports apparel manufacturing company,
Q83: Identifiable and noteworthy events marking significant progress
Q84: Which type of precedence diagramming convention is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents