Renly, a project manager in a construction company, has undertaken a project to construct a house. He estimates that the house will take 5 months to complete with his team of 10 workers. He also prepares a second estimate that allows the house to be completed in 2 months if 10 more workers are added to the team. Renly's second estimate is referred to as the _____.
A) crash duration
B) standard duration
C) slope duration
D) buffer duration
E) critical duration
Correct Answer:
Verified
Q42: According to research, the best overall priority
Q43: Victoria, a project manager, has undertaken a
Q44: A project that must be completed within
Q45: Hamid, a project manager, has a workload
Q46: The primary cause of concern in resource
Q48: A project that must be completed by
Q49: Which of the following priority rules makes
Q50: The task duration with standard-practice resource usage
Q51: Multitasking speeds up project completion.
Q52: The shortest-task-first priority rule for assigning resources
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents