Kimberley, a project manager in a software development company, is assigned a new project. She is given a budget of $500,000 and a span of six months to complete the project. In three months, she is able to complete 50 percent of the project. In this scenario, the earned value of the work completed is _____.
A) $350,000
B) $300,000
C) $250,000
D) $200,000
E) $150,000
Correct Answer:
Verified
Q60: Control is one of the project manager's
Q61: The SPI is calculated as…
A) AC /
Q62: In earned value analysis…
A) it is desirable
Q63: Estimated (remaining cost) to completion (ETC) is
Q64: Paulina, a fashion designer, has a new
Q66: The accountants of Junis Plex, a textile
Q67: The total cost to complete a task
Q68: Walter, a luthier, is assigned with the
Q69: The CPI is calculated as…
A) AC /
Q70: To calculate the variable in its economic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents