Eads Industrial Systems Company (EISC) is trying to decide between two different conveyor belt systems.System A costs $427,000,has a 6-year life,and requires $115,000 in pretax annual operating costs.System B costs $502,000,has an 8-year life,and requires $79,000 in pretax annual operating costs.Both systems are to be depreciated straight-line to zero over their lives and will have a zero salvage value.Whichever system is chosen,it will not be replaced when it wears out.The tax rate is 33 percent and the discount rate is 24 percent.Which system should the firm choose and why?
A) A; The net present value is $211,516.
B) A; The net present value is -$588,792.
C) A; The net present value is -$314,216.
D) B; The net present value is $308,222.
E) B: The net present value is -$612,240.
Correct Answer:
Verified
Q98: Chapman Machine Shop is considering a 4-year
Q99: Keyser Mining is considering a project that
Q100: Consider an asset that costs $176,000 and
Q101: Can the initial cash flow at time
Q102: How can two firms arrive at two
Q103: Assume a firm sets its bid price
Q105: In a single sentence,explain how you can
Q106: What is the formula for the tax-shield
Q107: What is the primary purpose of computing
Q108: Consider a project to supply 60,800,000 postage
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents