After performing additional tests of controls, the auditor reassesses control risk from the initial planning level of slightly below maximum to moderate. The auditor should now:
A) decrease the level of detection risk, and decrease substantive testing.
B) increase the level of detection risk, and increase substantive testing.
C) increase planned substantive testing.
D) increase the level of detection risk, and decrease substantive testing.
Correct Answer:
Verified
Q6: If the auditor decides to seek a
Q7: A disadvantage of the integrated test facility
Q8: After the auditor planned the audit based
Q9: The statement that is accurate concerning audit
Q10: Tests of controls are auditing procedures performed
Q12: When tests of controls are not performed
Q13: What is the purpose of the preliminary
Q14: Which of these would be a necessary
Q15: The timing of tests of controls refers
Q16: Based on a study and evaluation completed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents