Which of the Following Is Not a Benefit of Earned

Question 92

Multiple Choice

Which of the following is not a benefit of Earned Value Management?


A) Measures accomplishments against plan and deliverables.
B) Provides a method for tracking directly to a problem work package and organization unit responsible.
C) Enables the project manager to ascertain problem paths within the project network and when the critical path is underperforming.
D) Alerts all stakeholders to early identification of problems and allows for quick, proactive corrective action.
E) Provides for accountability over individual portions of the overall budget for each organization unit.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents