A CPI or SPI value less than one indicates that the project is currently
A) under cost or behind schedule.
B) over cost or ahead of schedule.
C) under cost or ahead of schedule.
D) over cost or behind schedule.
E) on cost or on schedule.
Correct Answer:
Verified
Q51: Baseline project budgets are derived from
A) the
Q52: Which of the following methods will measure
Q53: The earned value of a project is
Q54: The indicator that tells you the amount
Q55: The schedule variance for a project is
Q57: A project manager notices that $5,560 worth
Q58: A reason that the duration on a
Q59: Which of the following is NOT true
Q60: Which of the following are required to
Q61: _ is simply the percent complete times