A Process Breakdown Structure can provide a reasonable alternative to a Work Breakdown structure for an extensive development project if
A) phase exit criteria are firmly established.
B) there are appropriate predecessor relationships in place.
C) deliverables are tightly aligned to milestones.
D) tangible products are being developed.
E) risk planning is included early in the project.
Correct Answer:
Verified
Q42: Which of the following is least likely
Q43: All of the following are ways the
Q44: The integration of the lowest level of
Q45: The highest element in the hierarchical breakdown
Q46: The lowest element in the hierarchical breakdown
Q48: One way for a project manager to
Q49: The WBS is best suited for projects
Q50: A "Dissemination Mode" is
A) how project schedules
Q51: Having a strong communication plan can go
Q52: A Responsibility Matrix will clarify
A) tasks.
B) supports.
C)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents