Solved

You Have Just Been Given a Project That Has a Specific

Question 33

Multiple Choice

You have just been given a project that has a specific completion date. After a discussion with top management you find that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as


A) constrained.
B) reduced.
C) accepted.
D) limited.
E) optional.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents