Which of the following does NOT help describe a bottom-up estimating approach?
A) They are made by someone who uses experience and / or information from someone else to determine overall project cost and duration.
B) They establish low-cost, efficient methods for completing activities.
C) They typically come from the people actually doing the work and who are most knowledgeable about the task at hand.
D) Estimates are made at the work package level and then "rolled up" to determine estimates for major deliverables and for the project itself.
E) They can take place after the project has been planned in detail.
Correct Answer:
Verified
Q27: Which of the following is a good
Q28: The salary of the project manager would
Q29: A good starting point for developing time
Q30: Typical kinds of costs found in a
Q31: A home builder is collecting estimates for
Q33: Which of the following is NOT true
Q34: A project manager is looking over the
Q35: Accounting would be an example of which
Q36: Mega Projects often under deliver on expected
Q37: Which of the following is a good
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents