The table that shows each risk event as rows while columns will identify the name of the risk, the response to the risk, the contingency plan and the trigger is called what?
A) Responsibility assignment matrix
B) Risk response matrix
C) Risk identification table
D) Risk characterization table
E) Risk assessment matrix
Correct Answer:
Verified