A key distinction between a risk response and a contingency plan is
A) a risk response is established only for moderate risks while contingency plans are established for major risks.
B) a risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.
C) a risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.
D) a risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) a risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.
Correct Answer:
Verified
Q48: One of the following five choices is
Q49: Change management systems are designed to accomplish
Q50: Risks are evaluated in terms of
A) likelihood
Q51: One of the choices below refers to
Q52: Funds that are for identified risks that
Q54: Which of the following is NOT included
Q55: This response is used to remove any
Q56: Which of the following is NOT one
Q57: This response is used when an identified
Q58: A fixed price contract is an example
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents