A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
Correct Answer:
Verified
Q28: All of the following are types of
Q29: A project leader's boss has indicated that
Q30: In reviewing the status of a project
Q31: A project purchasing agent is trying to
Q32: A special truck that is needed on
Q34: Having individual staff members assigned to multiple
Q35: When developing a new software package, logically,
Q36: Most of the scheduling methods available today
Q37: Project managers should always assign the best
Q38: Project management software is important because it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents