The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
Correct Answer:
Verified
Q3: If a project needs one earth mover
Q4: A project budget report is showing our
Q5: Since resource leveling or smoothing delays noncritical
Q6: When scheduling activities in a resource-constrained project
Q7: Scheduling projects classified as resource-constrained focuses on
Q9: In a resource-constrained project, the completion date
Q10: Resource dependency takes priority over technological dependency
Q11: Having too few programmers and too many
Q12: The inability to fit more than two
Q13: A lack of readily available engineers is