When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?
A) Establish a core project team
B) Fast-tracking
C) Reduce project scope
D) Compromise quality
E) Use critical-chain project management
Correct Answer:
Verified
Q36: In a Project Cost-Duration Graph, total project
Q37: The shortest possible time an activity can
Q38: Insensitive networks are a rarity; Planning for
Q39: Intense global competition and rapid technological advances
Q40: A construction contractor finished a bridge across
Q42: When reducing project duration, the duration for
Q43: When determining which activity to crash, there
Q44: Which of the following is NOT one
Q45: Which of the following is NOT a
Q46: Which of the following correctly calculates an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents