The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
A) normal
B) reserve
C) crash
D) accelerated
E) expedited
Correct Answer:
Verified
Q19: There are more options available for reducing
Q20: Incentive contracts can make the reduction of
Q21: Crashing activities on a project network that
Q22: As a project is crashed and project
Q23: Resources are frequently over-allocated when crashing a
Q25: Before crashing, direct costs for an activity
Q26: One of the advantages of using a
Q27: Which of the following is NOT considered
Q28: The simplest way to reduce cost on
Q29: As a project is crashed and project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents