Solved

The AON Diagram Shown Represents a Project

Question 38

Multiple Choice

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed? The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each. The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each.


A) There is no economical way to reduce completion time.
B) Crash Activity 3 by 2 days.
C) Crash Activity 7 by 2 days.
D) Crash Activities 3 and 7 by one day each.
E) Crash Activities 2 and 3 by one day each.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents