The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?
A) There is no economical way to reduce completion time.
B) Crash Activity 3 by 2 days.
C) Crash Activity 7 by 2 days.
D) Crash Activities 3 and 7 by one day each.
E) Crash Activities 2 and 3 by one day each.
Correct Answer:
Verified
Q33: As a rule, each project includes a
Q34: A 5-year project requires $10 million in
Q35: Suppose that the crash cost is $10
Q36: In a single sentence, what is project
Q37: Define the process of project management.
Q39: Explain what the closure stage of a
Q40: In order to calculate the crash cost
Q41: What is the Work Breakdown Structure (WBS)?
Q42: How do we find a project's critical
Q43: What are the advantages and disadvantages of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents