Who is responsible for the detailed project plan?
A) the project's sponsor
B) the government
C) the Canadian Engineering Association
D) the project's manager
E) the financial institution who finances the project
Correct Answer:
Verified
Q5: Nodes and arcs are used in the
Q6: What does `PERT' stand for?
A)Probable Engineering Return
Q7: A Gantt Chart is
A)a chart that depicts
Q8: Finding ES, EF, LS, and LF requires
A)one
Q9: The lifecycle of a project is given
Q11: A fundamental advantage of the CPM networks
Q12: AON stands for
A)activity of a network.
B)activity on
Q13: For an engineering project, the justification for
Q14: What is the difference between a diagram
Q15: What does "WBS" stand for?
A)Weighted Brokerage System
B)Work