Sue and Kevin Kellman signed a contract for the construction of a cabin near Pinetop.In building the $562,000 cabin,the builder discovered that it had to put the vent for the heating system in the area where the hall closet is located.The result was that the Kellman's had a half-closet there instead of a full-length closet that was open to the floor.The Kellmans:
A) need not pay for the cabin because of this material breach.
B) can be compensated under the doctrine of force majeure.
C) can be compensated under the doctrine of commercial impracticability.
D) can be compensated under the doctrine of substantial performance.
Correct Answer:
Verified
Q108: Which of the following is prohibited under
Q109: The Fair Debt Collections Practices Act applies
Q110: Angela,age 17,is injured in a car accident
Q111: In order to recover damages under the
Q112: What rights does a debtor have if
Q114: Alice,age 17,purchased a 2005 Kia auto at
Q115: The Fair Credit Reporting Act applies:
A)only to
Q116: Costco,Inc.had a contract to purchase 300,000 electric
Q117: Which of the following would
Q118: The three-day-cooling-off period applies to:
A)credit contracts in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents