Which of the following statements regarding Gantt charts is TRUE?
A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) All of these are true.
Correct Answer:
Verified
Q29: Project managers often use the waterfall approach
Q30: PERT, but not CPM, has the ability
Q31: A(n) _ divides a project into more
Q32: Ill-defined projects are typified by software development
Q33: A combination of effective Gantt chart use
Q35: What is a project organization?
Q36: Identify the responsibilities of project managers.
Q37: Projects such as road building and plane
Q38: Gantt charts give a timeline for each
Q39: The control of projects involves close monitoring
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents