An x-bar control chart was examined and no data points fell outside of the limits. Can this process be considered in control?
A) Not yet, there could be a pattern to the points.
B) Not yet, the R-chart must be checked.
C) Not yet, the number of samples must be known.
D) Yes.
E) Both A and B
Correct Answer:
Verified
Q138: The Central Limit Theorem states that when
Q139: Mean charts and range charts complement one
Q140: A normal distribution is generally described by
Q141: Control charts for variables are based on
Q142: A manager wants to build 3-sigma x-bar
Q144: The number of late insurance claim payouts
Q145: Red Top Cab Company receives multiple complaints
Q146: Ten samples of a process measuring the
Q147: If = 23 ounces, σ = 1.0
Q148: Assignable causes:
A) are not as important as
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents