An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 90 minutes. The largest assigned cycle time is 20 minutes. What is the efficiency of this line?
A) 4.2 percent
B) 17 percent
C) 85 percent
D) 100 percent
E) 90 percent