Which of the Following Is NOT One of the Four

Question 5

Multiple Choice

Which of the following is NOT one of the four key tasks that Wheeled Coach insists are necessary for successful MRP implementation?


A) The material plan must meet both schedule requirements and facility capabilities.
B) The plan must be executed as designed.
C) Inventory investment must be minimized.
D) Excellent record integrity must be maintained.
E) The process must adhere to stringent quality control standards.

Correct Answer:

verifed

Verified