Question 33

Multiple Choice

A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 15, and 18 hours. What is the cumulative deviation in output?


A) 0
B) 1
C) −1
D) 58
E) Unable to determine with the given information