Riker Co. is considering which of 4 different projects to undertake in order to maximize its net present value (NPV) . Define Xi as a binary variable that equals 1 if project i is undertaken and 0 otherwise, for i = 1, 2, 3, 4. The NPV and required capital (in millions) for each project are listed below. Which of the following represents the constraint(s) stating that project 1 must be undertaken and at least one of the other projects must be undertaken?
A) X1 + X2 ≤ 1, and X1 + X3 ≤ 1, and X1 + X4 ≤ 1
B) X1 ≥1, and X2 + X3 + X4 ≥ 1
C) X1 + X2 ≥ 1, and X1 + X3 ≥ 1, and X1 + X4 ≥ 1
D) X1 ≥ 1, and X2 + X3 + X4 ≤ 3
E) X1 + X2 + X3 + X4 ≥= 2
Correct Answer:
Verified
Q92: A stereo mail order center has 9,000
Q93: Computer software provides a simple way to
Q94: The main disadvantage of introducing constraints into
Q95: The diet problem is known in agricultural
Q96: Binary variables can only take on the
Q97: The property manager of a city government
Q98: A financial advisor is about to build
Q99: Based on the number of meals sold
Q101: _ variables allow us to introduce "yes-or-no"
Q102: Describe how to incorporate fixed costs into
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents