Acme expected demand for rocket-powered roller skates to pick up during Roadrunner Season, so they built hundreds of extra pairs and stored them out of season. The excess production is:
A) buffer stock.
B) throughput.
C) lagniappe.
D) anticipation inventory.
Correct Answer:
Verified