
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?
A) It will not change.
B) It will increase by one week.
C) It will increase by two weeks.
D) It will increase by three weeks.
Correct Answer:
Verified
Q117: Information accuracy relative to the completeness of
Q118: Table 7.13
All activity times for the project
Q119: Table 7.3 Q120: Table 7.3 Q121: The phase of project management that takes Q123: Consider the activities, durations, and predecessor relationships Q124: The probability that a project will be Q125: The savvy project manager knew there would Q126: In addition to finishing the work, the Q127: The phase of project management that takes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents