Table 7.14 You Are Responsible for Managing a Project with the Following

Question 122

Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
 
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?
A) It will not change. 
B) It will increase by one week. 
C) It will increase by two weeks. 
D) It will increase by three weeks.

Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks) .    -Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase? A)  It will not change. B)  It will increase by one week. C)  It will increase by two weeks. D)  It will increase by three weeks.
-Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?


A) It will not change.
B) It will increase by one week.
C) It will increase by two weeks.
D) It will increase by three weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents