
Table 7.10
Four possible options exist to crash activities: crash A by one week at a cost of $6,000; crash C by two weeks at a cost of $15,000; crash E by one week at a cost of $2,000; and crash I one week at a cost of $7,000. What is the maximum amount of additional profit that can be made by crashing an option (or options) ?
A) less than or equal to $4,000
B) greater than $4,000 but less than or equal to $8,000
C) greater than $8,000 but less than or equal to $12,000
D) greater than $12,000
-If a project has exactly one critical path, which of the following statements is True?
A) Crashing an activity on the critical path will always result in an increase in total project profits.
B) Activities on the critical path cannot be crashed.
C) Crashing an activity on the critical path will always result in a reduced total project completion time.
D) The best schedule is one in which all activities are crashed as much as possible.
Correct Answer:
Verified
Q93: Table 7.9 Q94: You are given the following information about Q95: The _ is the shortest possible time Q96: You are given the following information about Q97: Table 7.9 Q99: The _ is determined by starting with Q100: A company could add $10,000 per week Q101: Table 7.14 Q102: When using the beta distribution for estimating Q103: Table 7.2 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents
You are responsible for managing a