Consider the following production process. It is trying to meet a market demand of 250 units per week.
Step 1: Material release schedule
Step 2: Drilling (capacity is 300 units/week)
Step 3: Tapping (capacity is 150 units/week)
Step 4: Grinding (capacity is 300 units/week)
Step 5: Coating (capacity is 200 units/week)
Step 6: Inspection (capacity is 500 units/week)
a. Where should buffers be placed?
b. Which resource is the drum?
c. Where should the rope be placed?
d. Which resource is the bottleneck?
e. Which resource is the CCR?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q126: Describe three ways that line balancing and
Q127: Balance the line in order to achieve
Q128: Balance the assembly line for the tasks
Q129: Consider the following production process. It is
Q130: Table 5.7
The Terminal Company is attempting to
Q131: Regardless of the number of tasks or
Q132: A(n) _ line is a product line
Q134: _ is the maximum time allowed for
Q135: Balance the assembly line using the following
Q136: How can Theory of Constraints principles be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents