A line balance that is 100% efficient must:
A) be using the minimum cycle time.
B) be using the theoretical minimum number of work stations.
C) also achieve 100% balance delay.
D) be producing the theoretical maximum output.
Correct Answer:
Verified
Q95: What is the definition of "theoretical maximum