Table 5.2
A company makes four products that have the following characteristics: Product A sells for $75 but needs $20 of materials and $20 of labor to produce; Product B sells for $90 but needs $45 of materials and $20 of labor to produce; Product C sells for $110 but needs $50 of materials and $30 of labor to produce; Product D sells for $135 but needs $75 of materials and $40 of labor to produce. The processing requirements for each product on each of the four machines are shown in the table.
Work centers W, X, Y, and Z are available for 40 hours per week and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.2. Using the bottleneck method, in what sequence should products be scheduled for production?
A) A, D, B, C
B) D, A, B, C
C) A, D, C, B
D) D, A, C, B
Correct Answer:
Verified
Q73: Table 5.3
King Supply makes four different types
Q74: Table 5.3
King Supply makes four different types
Q75: Table 5.1
A company makes four products that
Q76: Table 5.2
A company makes four products that
Q77: Table 5.2
A company makes four products that
Q79: Table 5.2
A company makes four products that
Q80: Table 5.3
King Supply makes four different types
Q81: Instead of dividing the total standard time
Q82: Table 5.3
King Supply makes four different types
Q83: Schmidt Industries makes four different snake traps;
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents