The third step in Theory of Constraints application, "subordinate all other decisions to Step 2," means that the analyst should:
A) wait for authorization before proceeding with any system-wide changes.
B) schedule non-bottleneck resources to support the bottleneck schedule.
C) seek to increase capacity of only the bottleneck resources.
D) seek to increase capacity of both the bottleneck and non-bottleneck resources.
Correct Answer:
Verified
Q7: The second step in Theory of Constraints
Q8: Use the process flow diagram to determine
Q9: A bottleneck is an operation that has
Q10: Consider consecutive processes A-B-C, where process A
Q11: Lanny discovers that the bottleneck is the
Q13: Use the process flow diagram to determine
Q14: The process with the least capacity is
Q15: The first step in applying the Theory
Q16: Work should be released into the system
Q17: The fourth step in Theory of Constraints
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents