Table J.11 Work Center Q45 Has Four Jobs That Just Arrived (The

Question 74

Multiple Choice
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.
 
-Using the information in Table J.11 and the shortest processing time (SPT) rule, what should be the sequence of jobs processed at Q45?
A) C-D-A-B 
B) D-A-C-B 
C) A-D-B-C 
D) B-A-D-C

Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.
Table J.11 Work center Q45 has four jobs that just arrived (the start of Day 1)  to be processed, as shown in the following table. Assume the shop works eight hours per day.    -Using the information in Table J.11 and the shortest processing time (SPT)  rule, what should be the sequence of jobs processed at Q45? A)  C-D-A-B B)  D-A-C-B C)  A-D-B-C D)  B-A-D-C
-Using the information in Table J.11 and the shortest processing time (SPT) rule, what should be the sequence of jobs processed at Q45?


A) C-D-A-B
B) D-A-C-B
C) A-D-B-C
D) B-A-D-C

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents