A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project?
A) $0 − $15K
B) $15.01K − $30K
C) $40.01K − $45K
D) $45.01K − $60K
E) Over $60K
Correct Answer:
Verified
Q86: Which of the following is not a
Q87: A project has four activities: A, B,
Q88: A specific event in a project is:
A)
Q89: Which of the following is not a
Q90: Which of the following is not a
Q92: This is a further subdivision of a
Q93: A project has four activities: A, B,
Q94: A project has four activities: A, B,
Q95: Which of the following takes the least
Q96: A project has four activities: A, B,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents