Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost?
A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.
Correct Answer:
Verified
Q57: A project starts out as which of
Q58: Currently, there are only two major companies
Q59: A company must perform a maintenance project
Q60: You are looking at a chart that
Q61: For an activity in a CPM analysis,
Q63: You have collected the data for a
Q64: A structure for organizing a project where
Q65: Popular project management software used in mid-sized
Q66: You have the following time and cost
Q67: In this structure, each project uses people
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents