Two jobs (J1 and J2) are to be scheduled on a single workcenter. J1 has a process time of 5 and J2 has a process time of 3. J1 has a due date of time 6 and J2 has a due date of time 7. If the jobs are scheduled by the SPT rule, in what order will they be processed?
A) J2 then J1
B) J1 then J2
C) Random order
D) The SPT rule is not related to processing order
Correct Answer:
Verified
Q31: Which job shop dispatch rule tends to
Q32: Two jobs (J1 and J2) are to
Q33: Scheduling jobs into the future based upon
Q34: Two jobs (J1 and J2) are scheduled
Q35: What type of rules determine which job
Q37: Which job shop dispatch rule schedules the
Q38: The average amount of time a job
Q39: The total elapsed time to complete a
Q40: Two jobs (J1 and J2) are scheduled
Q41: In a job shop, _ are used