Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average flow time of these jobs?
A) 0
B) 7
C) 14
D) Cannot be determined from the information given
Correct Answer:
Verified
Q4: If I is the input rate and
Q20: If a job shop is heavily congested,
Q21: The average of flow time minus processing
Q23: Which job shop dispatch rule schedules the
Q24: Two jobs (J1 and J2) are scheduled
Q26: Two jobs (J1 and J2) are scheduled
Q27: A simple, one-vehicle routing problem with the
Q28: Two jobs (J1 and J2) are scheduled
Q29: Two jobs (J1 and J2) are scheduled
Q30: What type of chart is often used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents