Direct inputs into the master production schedule include all of the following except?
A) Purchase orders
B) Aggregate production plan
C) Firm customer orders
D) Bill of materials
Correct Answer:
Verified
Q17: The analysis of supplier and customer information
Q18: Updating a customer's account in a bank
Q19: A customer paying a bill through a
Q20: A bank emailing monthly statements to a
Q21: Master production schedules are typically?
A) Hourly
B) Daily
C)
Q23: Management of parts required for end items
Q24: MRP refers to?
A) Material rejection planning
B) Material
Q25: A simple bill of material can take
Q26: Screws used in the assembly of bicycles
Q27: Direct inputs into an MRP system include