A noncritical path activity?
A) Has zero slack time
B) Contributes directly to the duration of the project
C) Has zero slack time and contributes directly to the duration of the project
D) Neither has zero slack time nor contributes directly to the duration of the project
Correct Answer:
Verified
Q84: A plan that is put in place
Q85: A government chooses to impose new regulatory
Q86: An activity with a slack time greater
Q87: A critical path activity?
A) Has zero slack
Q88: A contractor indicates that he will be
Q90: In a project, how many critical paths
Q91: When crashing a project, the project manager
Q92: When crashing a project, how many critical
Q93: An activity with a slack time of
Q94: A supplier indicates that he will not