The Z value is found by:
A) Z = (expected completion date) / project duration standard deviation
B) Z = (desired completion time - expected completion date) / project duration standard deviation
C) Z = (desired completion time) / project duration standard deviation
D) Z = (desired completion time - expected completion date) / project duration variance
Correct Answer:
Verified
Q57: Unrealistic activity time estimations would be an
Q58: Poor estimates of activity costs would be
Q59: Which of the following is not a
Q60: Unexpected events that may lead to missed
Q61: Expected activity completion time can be calculated
Q63: Within a complex project, all of the
Q64: A notable example of an open source
Q65: If project completion times are normally distributed,
Q66: An activity's early finish time minus late
Q67: Which of the following is widely used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents