After initial control chart construction, the third step to continue statistical monitoring of a process is?
A) Collect samples of size four or five periodically
B) Plot sample means and ranges on the control charts
C) If the process trends out of control, investigate the causes and eliminate assignable variations
D) Ensuring that the process is in control before beginning statistical monitoring
Correct Answer:
Verified
Q20: Variation that is attributable to a cause
Q21: The measure of the ability of a
Q22: An x-bar chart in which all points
Q23: A process with a Cpk value less
Q24: A process with a Cpk value greater
Q26: Which of the following refers to a
Q27: Producer's risk can result in what type
Q28: After initial control chart construction, the first
Q29: The A2 value for a sample size
Q30: A process with a mean output of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents