You are working on a bid to build two city parks a year for the next three years. This project requires the purchase of $249,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the three-year project life. Ignore bonus depreciation. The equipment can be sold at the end of the project for $115,000. You will also need $18,000 in net working capital for the duration of the project. The fixed costs will be $37,000 a year and the variable costs will be $148,000 per park. Your required rate of return is 14 percent and your tax rate is 21 percent. What is the minimal amount you should bid per park? (Round your answer to the nearest $100)
A) $212,500
B) $208,400
C) $214,300
D) $214,100
E) $208,200
Correct Answer:
Verified
Q77: Hunter's Hut is considering a project that
Q78: Overland purchased $387,950 of fixed assets that
Q79: A project will require $512,000 for fixed
Q80: Alt's is contemplating the purchase of a
Q81: Webster's has sales of $798,000 and a
Q83: PGH Inc. is considering a new seven-year
Q84: A two-year project has sales of $582,960,
Q85: Kwik Dogs is considering the installation of
Q86: A five-year project has an initial fixed
Q87: Marie's Fashions is considering a project that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents