If a project has a net present value equal to zero, then:
A) the total of the cash inflows must equal the initial cost of the project.
B) the project earns a return exactly equal to the discount rate.
C) a decrease in the project's initial cost will cause the project to have a negative NPV.
D) any delay in receiving the projected cash inflows will cause the project to have a positive NPV.
E) the project's PI must also be equal to zero.
Correct Answer:
Verified
Q14: A project has a required payback period
Q15: Which one of the following methods of
Q16: Which one of the following will decrease
Q17: Why is payback often used as the
Q18: Applying the discounted payback decision rule to
Q20: The average accounting rate of return (AAR):
A)
Q21: Assume a project is independent with financing
Q22: Southern Chicken is considering two projects. Project
Q23: The internal rate of return is defined
Q24: If a firm accepts Project A it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents