At a production level of 5,600 units a project has total costs of $89,000. The variable cost per unit is $11.20. What is the amount of the total fixed costs if the production level is increased to 6,100
Units without increasing the total fixed assets?
A) $24,126
B) $26,280
C) $27,090
D) $27,820
E) $28,626
Correct Answer:
Verified