Swan, Inc.uses the high-low method to analyze cost behavior.The company observed that at 22,000 machine hours of activity, total maintenance costs averaged $33.40 per hour.When activity jumped to 25,000 machine hours, which was still within the relevant range, the average total cost per machine hour was $30.40. On the basis of this information, what were total maintenance costs when Swan experienced 23,000 machine hours?
A) $193,200.
B) $550,000.
C) $734,800.
D) $743,200.
E) $760,000.
Correct Answer:
Verified
Q86: Barkoff Enterprises, which uses the high-low method
Q87: Shum Manufacturing, which uses the high-low method,
Q88: Tallequah, Inc.uses the high-low method to analyze
Q89: Fulton and Sons, Inc.presently leases a copy
Q90: Shum Manufacturing, which uses the high-low method,
Q92: The following data relate to the Torrence
Q93: Almed Products has determined that the number
Q94: Barkoff Enterprises, which uses the high-low method
Q95: The following data relate to the Torrence
Q96: The following data relate to the Torrence
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents